Chinook Intercare

Chinook Intercare

Description: Fire alarm verification for Chinook Intercare in Calgary, focused on confirming a booster programming change and system operation. Email correspondence also references Revenue 2022/2023/2024 / Invitation: -BFS @ Thu Jan 30, 2025 1pm – 2pm (MST) (Tim Alton).

Problem/Objective: Verify the fire alarm system following a booster programming change. The email thread suggests the immediate objective was to review and issue the required drawing or submittal updates.

Method/Process: Performed on-site fire alarm verification in line with CAN/ULC-S537 and referenced Alberta code requirements. The correspondence shows drawing review, revision tracking, and submittal coordination.

Result/Impact: Confirmed the system was operational at the time of verification. The thread points to delivery or issuance of the required documents.

Reflection: MNA learned from Chinook Intercare that care occupancies require extra attention to reliability, occupant protection, and authority-facing evidence; the project reinforced the value of turning limited source information into clear decisions, coordinated documentation, and practical next steps for the client.

Location: 1261 Glenmore Trail SW, Calgary, AB T2V 4Y8

Date: 2025-01-31