Description: Fire alarm verification and code-compliance review based on project submittal documentation. Scope noted in source: of: 2 alarm relays to Delta V Bldg B, ACWA Pumphouse South, and Delta V in ACWA WWTP Bldg P50B

Problem/Objective: Complete of: 2 alarm relays to Delta V Bldg B, ACWA Pumphouse South, and Delta V in ACWA WWTP Bldg P50B.

Method/Process: Reviewed project documentation and verified the fire alarm system against applicable CAN/ULC-S537 and Alberta Building Code requirements.

Result/Impact: Confirmed the fire alarm system was tested and operational at the time of verification, with the required CAN/ULC-S537 verification record issued for the project.

Reflection: MNA learned from Pine Creek that focused fire alarm verification at of: 3131 210 Ave SE for the depends on disciplined device-by-device evidence, clear drawing/submittal tracking, and early coordination with the client or AHJ so compliance can be closed without avoidable rework.