Description: Fire alarm verification and code-compliance review based on project submittal documentation. Scope noted in source: of: Adding duct detectors for RTU’s
Problem/Objective: Complete of: Adding duct detectors for RTU’s.
Method/Process: Reviewed project documentation and verified the fire alarm system against applicable CAN/ULC-S537 and Alberta Building Code requirements.
Result/Impact: Confirmed the fire alarm system was tested and operational at the time of verification, with the required CAN/ULC-S537 verification record issued for the project.
Reflection: MNA learned from Atrium Duct Detectors that focused fire alarm verification at 4014 Macleod Trail S, Calgary, AB T2G 2R7 depends on disciplined device-by-device evidence, clear drawing/submittal tracking, and early coordination with the client or AHJ so compliance can be closed without avoidable rework.
Location: 4014 Macleod Trail S, Calgary, AB T2G 2R7
Date: 4/1/2019