Description: Fire alarm verification and code-compliance review based on project submittal documentation. Scope noted in source: of: Relocate heat detector from celing to under t-bar tile
Problem/Objective: Complete of: Relocate heat detector from celing to under t-bar tile.
Method/Process: Reviewed project documentation and verified the fire alarm system against applicable CAN/ULC-S537 and Alberta Building Code requirements.
Result/Impact: Confirmed the fire alarm system was tested and operational at the time of verification, with the required CAN/ULC-S537 verification record issued for the project.
Reflection: MNA learned from Custom One Truck that focused fire alarm verification at of: 9230 51 St SE Calgary for the depends on disciplined device-by-device evidence, clear drawing/submittal tracking, and early coordination with the client or AHJ so compliance can be closed without avoidable rework.
Location: 9230 51 St SE Calgary
Date: 1/30/2023